I am on the executive committee for an apartment complex. We have had a number of requests from residents to add EV chargers to the basement carpark. It's obvious that the number of these requests will increase in the future, so we're trying to cater for the end goal - allowing everyone to install their own chargers. Of course, this requires that those chargers will be controlled by a central controller to prevent them from overloading the complex's electrical substation. My question is, what are the technologies available for distribution of power?
First, let me describe the physical infrastructure:
- We have a 500 kVA substation for the entire complex of 90 apartments.
- The average peak load is 175 kVA; the minimum (overnight) load is 55 kVA.
- The basement carpark is not a large square. Instead, think of a really stretched out 'S' shape, with the top and bottom curves quite tight - in other words, a long line of around 300m (1,000 ft). The substation and main switchboard are in the middle of the elongated 'S', so two 150m (500 ft) lengths.
- The basement carpark has a concrete ceiling with numerous existing services already installed: fire sprinkler system; sewerage and storm water piping; electrical cable trays; data cable trays; etc. It's quite "busy" up there - but there's nowhere else to install stuff.
Of the 90 units, to date there are only 5 applications for EV chargers. This will obviously increase, but the plan is for a phased installation to accommodate people as they put in their requests. The starting point is to install the master controller that all chargers will be controlled by, and a master utility electricity meter that will measure the total cost of electricity consumed. The master controller will log which chargers used how much power to allow us to bill the tenants for the power consumed. We're assuming that each space will only have a 7 kVA charger installed.
Our plan is to effectively distribute the whole complex's power to all the chargers. While this is overboard, it seems appropriate given that the overnight rate is only 10% of available power, leaving 90% available for the EV chargers. That means that SIGNIFICANT power will be distributed throughout the carpark.
My understanding of the technologies available suggest the following approaches:
- The traditional "tree" structure: feed multiple distribution boards (DBs), which in turn feed individual chargers as necessary. For example, for 90 apartments install 6 DBs of 15 apartments each, and then slowly add the individual cable runs from each car space to its nearest DB.
- Use a busway / busduct system to provide a "backbone" of power that individual car spaces can connect to. Extend the bus as more distant residents apply to be connected.
For 1), the problem is that even a single DB could conceivably require a LARGE amount of power at a time. 15 car spaces of 7 kVA each is over 100 kVA, requiring THICK cables for the feed. And since they each come from the central area to various places along the long line, the multiple THICK cable runs are parallel, which is expensively redundant!
The advantage of 2) is that there'd be a single "run" for the length of the carpark for the full power draw of the system. The problem is that busway / busduct is not very flexible. Dodging and weaving through the existing pipework infrastructure isn't easy, or perhaps even possible.
What I'm looking for is a hybrid of the two: a single, flexible backbone (in the twisty turny sense) for the length of the system, allowing for individual "tap off" points along the length. The problem is that a cable run of 500 kVA would require either absurdly thick cables, or so many parallel cables that the expense would be exorbitant.
Suggestions?